The major overhaul of the bridge over the Lunguta River near the village of Corten in Taraclia District is 40% complete, with the total cost of the project amounting to 15.7 million lei
The National Road Administration announced this, noting that 5.8 million lei (including VAT) have been spent on the repairs to date, representing 37.37% of the contract value. The planned completion date is April 2027. During the work, traffic will be directed along a bypass road, and road users are asked to observe temporary road signs installed at the construction site. The bridge modernization will improve safety and traffic conditions for both residents of Taraclia District and all road users traveling along this section of the road. The mentioned bridge, located on the national road R37 Ceadîr-Lunga-Taraclia-R32, at 6+750 km, was built in the 1970s, its total length is more than 31 meters. // 17.06.2026 — InfoMarket.